National Theatre, Doha Qatar
DOHA
QATAR
LSI
Projects with local partners MDS in Doha were contracted for the complete Technical
Refurbishment of the 1980s built Qatar National Theatre.
The fast track refurbishment was completed in the latter part of 2004 and included
the Supply, installation and Commissioning of new stage engineering, stage lighting,
sound, video projection and communications systems.
The Project:
| Client |
National Council for Culture and Heritage |
| Theatre Consultants : |
ACT Consultants Ltd - UK |
| Start Date : |
March 2004 |
| Finish Date : |
September 2004 |
|
|
|
|
Under Construction
|
Main Foyer |

Deliveries Begin
May 2004
EQUIPMENT SUPPLIED & INSTALLED
LIGHTING:
Top of the range ADB Phoenix 10 lighting Console
Digital Plug - In Dimmer system
Over 150 Theatre Luminaires
A Working light, House light and Motor Control System
|
|
|
Phoenix 10
Lighting Control Console
|
SOUND:
Allen & Heath 32 and 24 channel mixers
Labgruppen amplifiers
L Acoustics loudspeaker system
|
|
|
| Control console |
Fully Populated Equipment Racks
|
EQUIPMENT SUPPLIED & INSTALLED
STAGE ENGINEERING:
New stage orchestra pit elevator
A revolving stage
8 motorised bars,
36 counterweighted BARS
|
|
|
| Installation Of Counterweight Systems |
PROJECT MANAGEMENT & INSTALLATION
On - site Project Management and over 100 installation staff were provided by
LSI Projects. This included both electrical and mechanical installation for
all Production related equipment including Lighting, Sound, Stage Engineering
and all related electrical distribution/patch panels.
|
|
|
| Positioning of equipment racks |
Power and patch panels |
PROJECT COMPLETION
COMMISSIONING:
All Systems were commissioned during September/October ready for the first performance
on 12th December 2004.